PRIMAVERA ERP Integrator FAQs

How to integrate consumptions/consumptions under contract without an internal request?

49 views 29 January, 2017 29 January, 2017 Valuekeep 0

When integrating Valuekeep with the ERP, there are two flows for reporting material consumption:

  • Internal request required
    • you can only report consumptions and consumptions under contract when the contract manages stock if there is an internal request associated with the work order;
  • Internal request not required
    • you can report consumption and consumption under contract when the contract manages stock without an internal request.

To integrate consumptions/consumptions under contract with stock management without internal request, follow these steps:

  1. Access Configuration Tables | Work Orders | Work Order Types;
  2. Select the type of work order for which you want report consumptions without the requirement of an internal request;
  3. Enable the “Must not emit stock issue” option.

 

If the “external integration” option is active and the type of work order does not include stock issuing, you cannot edit consumptions/consumptions under contract with stock management. You can only delete them.
If the “external integration” option is enabled and the type of work order does not issue stock, consumption is created with the zero value for price and total and when the document is integrated, these fields are updated with the value present in the ERP.
Tags:

Foi útil?