Work Orders Explorations

Work Order Tasks by Employee

91 views 18 January, 2017 20 December, 2017 Valuekeep 0

From this list you can see the maintenance tasks assigned to an employee in each work order, by maintenance plan and task.

Here you can see information regarding:

  • Task start and end dates;
  • Expected execution times;
  • Actual times reported;
  • Difference between expected and reported times;
  • A sum of the fields concerning times.

By using the existing filters you can analyze the data displayed by Work Center, Employee, Work Order State and WO Date. You can filter data by the task start and end date using the quick filters at the header of the grid column.

You can also drilldown from the Work Order into the Costs Report.

Please note that the task start and end dates displayed are those from the Labor tab in the Costs Report screen and not those displayed on the Work Order Execution screen.

 

 

 

Foi útil?